Ivan, has this been posted? wind tunnel...

Recommended Posts

Probably, but if not.. Anyone else heard of this?

www.extremebodyflight.co.uk


Looks like its going to be pretty good. I dont know, no tunnels in the UK, then all of a sudden theres 2!

From what i hear about the prices, its not going to be too bad either, just wish it was a bit closer :(
Phoenix Fly - High performance wingsuits for skydiving and BASE
Performance Designs - Simply brilliant canopies

Share this post


Link to post
Share on other sites
talk has but i've not seen the link before.

Thats an awsome diagram comparing its size to other tunnels... at at over 150mph! Nice to think that the UK will be leading the world in wind tunnles from aug... at least for a while.

And £6 a minute - sweetos!:)

Share this post


Link to post
Share on other sites
Correct me peeps if i'm wrong, but i think this one will be open sooner, most of its already in place whereas the milton one has yet to be built from scratch?
Phoenix Fly - High performance wingsuits for skydiving and BASE
Performance Designs - Simply brilliant canopies

Share this post


Link to post
Share on other sites
The last I heard on the Milton Keynes one was that they were still a couple of mil short of their investment target. Unless they got it they will not be going ahead.

I also suspect they won't be able to match the price this one offers either as they have to build from scratch. The one in Bedford only has to renovate MOD buildings.

Given the announcement that Bedford one is going ahead I wonder if they Milton one will even get off the ground... if they do I worry if there will be enough buisness to keep them both working - Milton and Bedford are too close for comfort and I think 1 is all the UK market can handle. It would be a shame to see two open and then drive each other under.

Share this post


Link to post
Share on other sites
Quote

The skyventure site says they are aiming for the second quarter of 2004. Anyone know if this is realistic?



I would think the project would need a minimum of a year for detail design and construction. This depends on how much upfront work has been done, whether sub-contract tendering has taken place so that when funds are in place contracts can be immediately placed (for the steel frame and cladding for instance)

If the August 2004 is realistic the Bedford tunnel will open first.



"Life is a bowl of deadly nightshade, stay way way out on the rim brother"

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

0